근로시간 단축에 따른 건설 공사의 공사비 영향 분석 - 직접 노무비 중심으로 -

원문정보

Analysis of the Impact of Construction Cost of Construction Work due to the Reduction of Working Hours - Focusing on Direct Labor Costs -

조선영, 최재혁, 김상용

피인용수 : 0(자료제공 : 네이버학술정보)

초록

영어

From July 1, 2018, the policy called the maximum 52-hour workweek was enforced. This policy became a challenge the construction site should solve. Compared to other industries, the construction industry more relies on human resources. Moreover, in the construction industry, it is essential to complete a building within a set period of time. However, the 52-hour workweek policy has reduced working hours from before, making it difficult to finish construction work within a fixed period of time. Considering these characteristics of the construction field, the government implemented some policies, such as the increase in the number of workers deployed at construction sites and the flexible working system. However, it is still difficult to meet the construction period. Therefore, this study focused on changes that would be occurred since working hours have been reduced from the 68-hour workweek to the 52-hour workweek. In conclusion, it has been analyzed that the construction period has been prolonged due to the reduction of working hours caused by the 52-hour workweek system, and the ratio of labor costs to total construction costs has decreased.

목차

Abstract
1. 서론
1.1 연구배경 및 목적
1.2 연구범위 및 방법
2. 선행연구 및 정책 분석
2.1 근로시간 관련 정책 분석
2.2 노무비 산정을 위한 관련 문헌 고찰
3. 근로시간에 따른 공사기간 및 직접노무비 분석
3.1 분석 방법
3.2 공정표 분석
3.3 소요일수 및 노무비 산정
3.4 분석 결과
4. 결론
REFERENCES

저자정보

  • 조선영 Cho, Sun Young. 영남대학교 건축공학과 석사과정
  • 최재혁 Choi, Jae Hyuk. 영남대학교 건축공학과 석사과정
  • 김상용 Kim, SangYong. 영남대학교 건축학과 부교수, 공학박사