In a typical three-phase four-wire or three-phase three-wire power system, the load-to-load balance shall be achieved if the load is installed between the power lines and the neutral lines on each phase and between each power line. If a particular power line is overloaded, excessive current may continuously flow through the windings, such as transformers installed on the power line, which may accelerate insulation deterioration of the windings. In fact, fires frequently occur at industrial sites depending on unbalanced facilities for load facilities, and the damage is increasing due to the failure to accurately identify the cause of the fire. Through this case study, the three-phase, three-way power system is designed to identify the risks associated with unbalanced facilities of the load facilities and to take preventive measures against them.
한국어
일반적인 3상 4선식 또는 3상 3선식 전력계통에서 각 상의 전원선과 중성선 그리고 각 상의 전원선 사이에 부하가 설치되는 경우 전원선 사이에 부하의 평형이 이루어져 야 한다. 특정 전원선에 부하설비가 과도하게 시설되어 사용된다면, 그 전원선에 설치 된 변압기 등의 권선에 지속적으로 과도한 전류가 흐르게 되어 권선의 절연열화가 가 속될 수 있다. 실제로 산업현장에서 부하설비 불평형 시설에 따라 화재가 빈번히 발생 되고 있으며, 화재원인에 대한 정확한 규명을 하지 못해 그 피해는 증대되고 있다. 이 에 본 사례연구를 통하여 3상 3선식 전력계통에서 부하설비의 불평형 시설에 따른 위 험성을 확인하고 그에 대한 예방대책을 강구하고자 한다.
목차
Abstract
1. 서론
2. 발화위험
3. 내선규정
4. 화재사례
4.1 일반사항
4.2 화재경위
4.3 발화원인
5. 결론
참고문헌