Identification & Analysis of Cost Overrun Risk through Cause Analysis of Contract Change of Public Construction Project
초록
영어
This study discriminated 62 detailed risk factors and analyzed the risks with FMEA method by grasping the factors of rising construction cost through cause analysis of contract change to discriminate and analyze cost overrun risk in the phase of executing public construction project. As its results, it was evaluated that construction period is larger than the factors of construction cost by 1.3% in RPN analysis, and as the result of analyzing the correlation of risk against rising if construction cost and delay of construction period, it appeared that rank correlation coefficient has the strong correlation with 0.892. And, it showed that Project Character-related(PC), design quality-related(DQ) items were high in the criticality analysis and key risk factors that RPNC & RPNT values are above the average were 24. Based on the results of discriminating & analyzing cost overrun risk of this study, it is expected that the efficient management system of cost overrun risk can be arranged.
한국어
본 연구는 공공건설사업 시공단계에서의 공사비 상승리스크 식별 및 분석을 위하여 계약변경 원인 분석을 통한 공사비 상승요인을 파악하여 62개의 세부 리스크 요인을 식별하고 FMEA기법으로 리스크를 분석하였다. 그 결과, RPN 분석에서는 공기가 공사비 측면보다 1.3% 큰 것으로 평가되었으며, 공사비 상승 및 공기지연에 대한 위험도 상관관계 분석결과, 순위 상관 계수가 0.892로 강한 상관관계가 있는 것으로 나타났다. 또한, 리스크 항목별 중요도 분석에서는 프로젝트 특성(PC), 설계품질 관련(DQ) 항목이 중요도가 높았으며, RPNC, RPNT 값이 평균이상인 핵심 리스크 요인은 24개로 나타났다. 본 연구의 공사비 상승리스크 식별 및 분석결과를 바탕으로 시공단계에서의 효율적인 공사비 상승리스크 관리시스템을 마련 할 수 있을 것으로 기대된다.
목차
1. 서론
1.1 연구배경 및 목적
1.2 연구범위 및 방법
2. 이론적 고찰
2.1 기존 연구 고찰
2.2 공공건설사업의 특성 및 계약변경으로 인한 영향
2.3 공공건설사업 공사비 상승리스크의 개념 및 분석방법
3. 공공건설사업의 공사비 상승리스크 분류체계 구축
3.1 계약변경 원인 분석을 통한 공사비 상승요인 도출
3.2 공공건설사업의 공사비 상승리스크 식별
4. 공공건설사업의 공사비 상승리스크 분석
4.1 조사개요
4.2 RPN(Risk Priority Number)분석
4.3 종합분석
4.4 핵심 공사비 상승리스크 요인 도출
5. 결론
참고문헌