Operating Current for the application of 22.9kV hybrid SFCL to real power grid in Korea
초록
영어
In Korea, 22.9kV hybrid SFCL (Superconducting Fault Current Limiter) has been developed and carried out long-term field tests in Gochagn power test center of KEPCO through DAPAS program. The SFCL will be installed at a distribution line of Icheon substation in Korea. For the successful application, we have to design the specifications considering real power system operation. This paper proposes a concept of the operating current based rms value for the protection coordination with protective delays and studies a proper range of the current in Korean distribution power system.
목차
1. 서론
2. 초전도한류기 동작전류 개념
3. 동작전류 설계방안
3.1. (1안) R/C단 고장전류 이상에서 동작
3.2. (2안) 배전선로 돌입전류에 동작
4. 동작전류 설계사양 검토
4.1. 동작전류 설계방안 제안
4.2. 동작전류 설계사양
4.3. 이천변전소 초전도한류기 고장전류 제한효과
5. 결론
참고문헌