Analysis of Bus Voltage Sag Caused by Recloser-Fuse Coordination in a Power Distribution System with SFCL
초록
영어
This paper analyzed bus voltage sag caused by recloser-fuse coordination in a power distribution system with SFCL. Generally, the recloser is installed to upstream of fuse to clear against both permanent and temporary faults appropriately, when the fault happened and to block expansion of the fault area. Futhermore, when the fault occurred, bus voltage sag is caused by increased fault currents. However, in a power distribution system with SFCL, the fault current could be decreased by the effect of the impedance value of the SFCL and place to install one as long as it could improve bus voltage sag. Therefore, to analyze the effect of the improvement of bus voltage sag caused by recloser-fuse coordination in a power distribution system with SFCL, we used PSCAD/EMTDC about a permanent fault at the place behind the fuse.
목차
1 . 서론
2. 본론
2.1. 보호기기 동작 특성
2.2. 모의 배전계통 구성
2.3. 배전계통에서의 순간전압강하
2.4. 리클로져-퓨즈 협조동작시 순간전압강하 분석
2.5. 초전도한류기 Case1 적용시 리클로져-퓨즈 협조동작에 따른 순간전 압강하 분석
2.6. 초전도한류기 Case 2 적용시 리클로져-퓨즈 협조 동작에 따른 순간전 압강하 분석
2.7. 결과 및 분석
3. 결론
참고문헌